What we build
Power distribution, transformer stations, lighting, solar, switchboards and controls — one supplier, one inspection report.
From the transformer station to the last distribution board
Questions that come up before the first meeting
How long does it take to connect a new hall to the grid?
It is decided by the distribution company and the capacity available locally, not by the installation work. That is why we file the connection request at the design stage — [X] months before production is due to start.
Can you work during live production?
Yes. We plan refurbishments in phases and carry out switchovers during shutdowns agreed in advance — typically a weekend or a night shift.
Do you buy switchboards or make them?
We make them. LV switchboards to STN EN 61439 with a declaration of conformity and routine testing before dispatch. You do not wait for a supplier and changes are handled directly.
Is solar worth it on a hall?
For daytime operations, usually yes — the hall consumes most of the output directly. We calculate the payback from your real consumption data, not from a table.
What do we receive at handover?
An inspection report, as-built drawings, test protocols, manuals and operator training — documentation that both the building authority and your insurer will accept.